Tweed Shire Council · Footpath Repair Program · QU3000356

Banora Point footpath repairs — 31 site quotes

Priced quote for each site, ready for Schedule 2 (GST-inclusive per ID). Tap any row to open that site's full quote: scope, slab detail and every priced line.

Summary

IDLocationDefectAreaWorkReplace m²Grind m²Ex GSTInc GST

Area groups A–F cluster nearby sites so they can be programmed together.

Council specification (TSC S.D.013 Rev E)

  • Footpath 1200 wide × 100 deep; cycleway 2500–3000 wide × 100 deep (150 where vehicles cross)
  • 50 mm compacted crusher dust bedding; subgrade to 95% standard compaction
  • SL72 mesh central, 40 mm cover; N25 concrete; broom finish; 20 mm rounded edges
  • Saw joints 0.25 × depth at max 1.5 × width, cut 24–36 hrs after pour
  • Expansion key joint every 4th joint and at green-pour junctions
  • R12 galvanised dowels 400 long @ 400 crs into existing path at each end
  • Tripstops at root damage and equidistant either side
  • Crossfall 1.0–2.5%; finish flush with turf (Council turfs)
  • Council supplies traffic control plans, controllers and signage (48 hrs notice)
  • 3 clear days' written notice to residents; work 7 am–5 pm Mon–Fri, up to 9 hrs/day

Site sheets